1
|
|
|
2
|
- $1,800,000 budget
- 10 classrooms
- New administration area
- Hallways, restrooms, storage
- Defined entrance to Pomona
- Remodel the current maintenance warehouse to become part of Pomona
|
|
3
|
- Bahr, Vermeer, Haecker Architects - Colorado Springs CO
- Carl Vostaek - Clifton CO
- Cole + Russell Architects – Denver CO
- D & K Contractors – Montrose CO
- FCI Constructors – Grand Junction CO
- Gateway Construction - Grand Junction CO
- Grey Wolf Architecture - Denver CO
- JHL Constructors – Englewood CO
- Ridgway Valley Enterprises, Inc. – Montrose CO
- The Neenan Company - Fort Collins CO
- Thira, Inc.(Architects) - Steamboat Springs CO
- Van Tilburg, Banvard & Soderbergh (VTBS) Architects - Denver CO
|
|
4
|
- Victor Lopez – Parent
- Nichole Schiebel – Parent
- Shay Freeburg – Parent
- Kristi DeVencentis – Parent
- Kelly Thompson – Music
- Mike Medina – Art
- Jessica Blacker – 4th Grade
- Kim Evink – Custodian
- Pam Stuckey – SPED
- Chuck Terrell – PE
- Betty Golle – Secretary
- Patty Casebier – Literacy
- Tom Hill – Principal
- Jason Arebalos
- Karin Slater
- George Voorhis
|
|
5
|
- D & K Contractors – Montrose CO
- JHL Constructors – Englewood CO
- Ridgway Valley Enterprises – Montrose CO
- The Neenan Company - Fort Collins CO
- White/BVH – Denver, Colorado
|
|
6
|
- The Neenan Company
- Prior school experience
- On-time, on-budget delivery
|
|
7
|
|
|
8
|
- January 2007 ~ Design Build Contract to the School Board for approval
- February 2007 ~ Groundbreaking
- August 2007 ~ Move in
|
|
9
|
- Tomorrow morning at 8:15 a.m.
|
|
10
|
- …..do you have any questions?
|