Construction Update
  • December 12, 2007


2
Pomona Elementary Addition
  • $1,800,000 budget
  • 10 classrooms
  • New administration area
  • Hallways, restrooms, storage
  • Defined entrance to Pomona
  • Remodel the current maintenance warehouse to become part of Pomona
3
Firms Requesting RFPs on the Pomona Project

  • Bahr, Vermeer, Haecker Architects - Colorado Springs CO
  • Carl Vostaek - Clifton CO
  • Cole + Russell Architects – Denver CO
  • D & K Contractors – Montrose CO
  • FCI Constructors – Grand Junction CO
  • Gateway Construction - Grand Junction CO
  • Grey Wolf Architecture - Denver CO
  • JHL Constructors – Englewood CO
  • Ridgway Valley Enterprises, Inc. – Montrose CO
  • The Neenan Company - Fort Collins CO
  • Thira, Inc.(Architects) - Steamboat Springs CO
  • Van Tilburg, Banvard & Soderbergh (VTBS) Architects - Denver CO
4
Pomona Design Team
  • Victor Lopez – Parent
  • Nichole Schiebel – Parent
  • Shay Freeburg – Parent
  • Kristi DeVencentis – Parent
  • Kelly Thompson – Music
  • Mike Medina – Art
  • Jessica Blacker – 4th Grade
  • Kim Evink – Custodian
  • Pam Stuckey – SPED
  • Chuck Terrell – PE
  • Betty Golle – Secretary
  • Patty Casebier – Literacy
  • Tom Hill – Principal
  • Jason Arebalos
  • Karin Slater
  • George Voorhis
5
Firms invited to Pomona for an interview

  • D & K Contractors – Montrose CO
  • JHL Constructors – Englewood CO
  • Ridgway Valley Enterprises – Montrose CO
  • The Neenan Company - Fort Collins CO
  • White/BVH – Denver, Colorado
6
Firm Selected
  • The Neenan Company
    • Prior school experience
    • On-time, on-budget delivery
7
 
8
Schedule
  • January 2007 ~ Design Build Contract to the School Board for approval
  • February 2007 ~ Groundbreaking
  • August 2007 ~ Move in
9
Oak Grove Ribbon Cutting
  • Tomorrow morning at 8:15 a.m.
10
Thank you…..
  • …..do you have any questions?