Notes
Slide Show
Outline
1
Construction Update
  • January 8, 2007


2
Pomona Design Team
  • Victor Lopez – Parent
  • Nichole Schiebel – Parent
  • Shay Freeburg – Parent
  • Kristi DeVencentis – Parent
  • Kelly Thompson – Music
  • Mike Medina – Art
  • Jessica Blacker – 4th Grade
  • Kim Evink – Custodian
  • Pam Stuckey – SPED
  • Chuck Terrell – PE
  • Betty Golle – Secretary
  • Patty Casebier – Literacy
  • Tom Hill – Principal
  • Jason Arebalos
  • Karin Slater
  • George Voorhis
3
The Neenan Company
  • School building experience
  • On-time delivery
  • On-budget programs
4
 
5
 
6
 
7
Pomona Elementary Addition
  • $155,897 – Design & Pre-Construction
  • $1,948,711 – Construction
  • 10 classrooms
  • New administration area
  • Hallways, restrooms, storage
  • Defined entrance
  • Remodel current maintenance warehouse
  • Demo current admin building
8
Schedule
  • February 2007 ~ Design Review
  • February 12 ~ Mobilization
  • February 14 ~ Ground Breaking!
  • August 3, 2007 ~ Certificate of Occupancy
9
Thank you…..
  • …..do you have any questions?